Power disruption in Computer Room 1 on 22 and 23 Aug 2016

Dear all,

As part of our Integrated Systems Testing (IST) following the infrastructure upgrading works in
Computer Room 1, we will shutdown outgoing power on both Source A and Source B, but never both at
the same time. The IST will take place from 10am to 6pm on 22nd and 23rd August 2016.

If your servers and other network equipment are connected to both Source A and Source B, you should
not be affected by the IST. Power will always be available on either Source A or Source B at any
one time. However, there will always be a risk of an accidental power supply trip or other unforeseen glitches.

 